Ministry of Water Resources - Ministry Projects

Projects 2006

Project Title Ministry ID PMO ID LOCATION(GOVERNORATE) Description Total Estimated Project Cost SDate EDate
Al Jazira Irrigation Pumping Station Rehabilitation PS-025 W-R-WR-PS and G-082 Ninewa Upgrade security and communications. Repair new cooling water pumps. Acquire three sets of spare control system parts. Continue or initiate a project appropriate security staff and procedures. Restore and upgrade an organization-wide communication system. Immediate: Pumping station cooling water supply pumps need repairs and spare parts for the plant controls. Plant reliability and the irrigation of 60,000 hectares are at high risk. Short Term: Initiate design of new PC-based control system. $1,776,000 10/1/2006 4/30/2007
Al Rumitha Reclamation Project Major-026
Muthanna Project is for irrigation and drainage. Includes lining of concrete canals, also fill drains, main drains. Reclamation of 10000 hac. `It has been estimated based on historical reclamation projects that the cost generally averages 1500 per hectare. This price includes all lining. $15,000,000 6/1/2006 11/30/2007
Construction of Basora Dam Dam-019
Suliamaniyah Construction of Basora Dam for purposes of water storage.. Dam is 53 m height, 350 m length. 2600 hac. This dam is also a ground water recharge upstream of the dam as well as irrigation downstream of the dam. Basora dam regulates water in one of the branches (small river) of Al Adhaim Dam. This dam is located on the Tawouk Chai River. It is Southwest of Suliamaniyah City. $40,000,000 3/1/2006 8/31/2007
Diwaniya Saffiya Reclamation Project Major-029 W-R-WR-Irrigation and Drainage-227 Qadisiyah Improve land productivity in this region; provide water resource; improve decreasing groundwater level; increase food production; provide increased work opportunities, provide initial requirement for local industry; and improving the quality and quantity of the livestock production. The project includes the construction of a complete irrigation and drainage system. The irrigation network is divided into three parts, each irrigated by a main canal, as follows: 1. MC1 canal, 17,800 hectares, left side of Shatt Al-Diwaniya, 1 pumping station 2. MC3 canal, 48,600 hectares, left side of Shatt Al-Diwaniya, 1 pumping station 3. MC2 canal, 87,000 hectares, left side of Shatt Al-Diwaniya, 1 pumping station. The drainage network comprises of 2 main drains, MD1 (on the left side of the project) and MD2 (on the right side of the project). MD1 goes to the Rumeitha drain (D3) at km 26.400 via pumping station; the length of this drain is about 42.120 km and it serves about 37,000 Hectares. MD2 goes to the Euphrates eastern drain at km 40.300 via pumping station; the length of this drain is about 58.100 km and it serves about 57,750 hectares. The project locates in Euphrates river basin to the south of Baghdad city about 200KM and it goes along the 2 sides of Shatt Al Diwaniya – from the north of Al Diwaniya to Al Najmi canal which is branched from the left of Shatt Al Diwaniya –The south of Al Hamzah city. Shatt Al Diwaniya which is branched from Shatt Al Hilla tails is considered the main source of irrigation in the project’s area. A. Irrigation network : According to the proposal of developing irrigation network of Al Diwaniya – Shafi`ya project, this project is divided into 3 parts each part is irrigated by a main canal, and as the following: • The 1st part: It is irrigated by the canal (MC1) for a net area which is about (31880) acres and it locates to the left side of Shatt Al Diwaniya. • The 2nd part: It is irrigated by the main canal (MC3) for a net area which is about (113608) acres and it locates to the left side of Shatt Al Diwaniya also. • The 3rd part: It is irrigated by the main canal (MC2) for a net area which is about (202960) acres and it locates to the right side of Shatt Al Diwaniya. In addition to the above canals, this network includes minor feeding & distributing canals lined with concrete. B. Drainage network: The proposed drainage network for the project comprises of 2 main drains– one of these drains is on the left side of the project, & this main drain is called (MD1), the other one is on the right side, & it is called (MD2). The drainage of the drain ( MD1) goes to Al Rumeitha drain (D3)at the kilometer (26,400) via pumping station , the length of this drain is about (42,120) KM into which many minor & collecting drains flow , and it serves about (31435) hectares . The drain (MD2) serves net area about (49049) hectares, its drainage goes to Euphrates eastern drain at the kilometer (121) via pumping station to raise water at the kilometer (40,300), its length is about (58,100)KM into which many minor & subsidiary drains flows. In addition to what is mentioned above, the irrigation & drainage networks comprise of necessary structures and they are: regulators of canals upstream, cutting regulators, pedestrian & cars bridges, and those structures also include drainage & intersections outfalls. Three irrigation pumping stations has been defined, one to the upstream of each main canal & two pumping stations (raising drainage) one in each main drainage. $37,305,000 3/1/2006 9/30/2084
Eastern Gharraf Reclamation Project Major-021 W-R-WR-Major-207 Wassit Improve land production in this region; provide water resource; improve decreasing groundwater level. The entire project area covers approximately 118,750 hectares, 75,000 in ThiQar governorate and 43,750 in Waseet governorate. $38,158,000 10/1/2006 4/30/2007
Hilla Kafil Reclamation Project Major-031 W-R-WR-Major-217 Babylon Improve land production. Provide a water resource. Slow decreasing groundwater levels. Reclaim 5,400 hectares on the right side of the Euphrates River, west of the Hella River, and to the north of the Hella-Kafil Road. The proposed work is to irrigate the southern portion of the Irrigation Project. $23,022,000 3/1/2006 8/31/2007
Hilla-Dewaniya Reclamation Project Major-027 W-R-WR-Major-214 Babylon Improve land production in this region; provide water resource; improve decreasing groundwater level. Project consists of reclamation through construction of new irrigation and drainage networks with associated structures, and irrigation and drainage pump stations. The project covers a total area of approximately 292,000 hectares. $191,853,000 4/1/2006 9/30/2006
Iskandriya-Mahawell Projects IR-024
Babylon To improve and increase the agricultural lands; provide water resource; improve decreasing groundwater level. The project will consist of construction of concrete-lined irrigation canals, a drainage system, and required structures. $15,000,000 6/1/2006 11/30/2007
Khazir-Komal Irrigation Project Construction IR-020
Arbil Construction of the project, have relation with Bakerman Dam. The project can be irrigated only after Bakerman regulating dam construction. This project covers a net irrigated area about 31900 ha. By mean of two main canals, the west canal which is about 44km and covers 12400 ha and the east channel which covers 19500 ha. All farms in the project irrigated by solid set sprinkler machine. The project consists of Bakerman and Kalikan regulating dam, with hydropower and net irrigation work. The project is located about 40 km NE of Mosul and covers the land of Zab and Tigris basin in Aqra and Shekan Qatha $20,000,000 8/1/2006 1/31/2007
Left Al-Adheem Reclamation Project (Ausser Eudhaim) (Phase II) Major-009
Diyala Continuation of Left Al-Adheem Reclamation Project (Ausser Eudhaim) (Phase I) Improve land production in this region; provide water resource, widen the agricultural area and to improve the economical and socials status of the people who live in this area. Approximately 90% of the people in this area (roughly 15,000 persons) are dependent upon agriculture for their livelihood. It includes 25,250 hectares. The project will consist of construction of concrete-lined irrigation canals, a drainage system, and land leveling for the first stage of 10,250 hectares (Sector 7 of Kirkuk Project). The project area lies roughly 40 kilometers from Khalis, to the south of the Eudhaim River, north of the Tigris River and north of the Al-Nai Reclamation Project. Source water is the Al Adhaim River. The proposed irrigation system will utilize existing topography as much as practicable. $15,000,000 5/1/2006 10/31/2007
Lining of Al Ishaki Western Canal IR-011
North Baghdad Lining Al Ishaki Western Canal; lining of canal with .1 m thick concrete including earth works to complete the required canal sections such as excavation, backfilling, trimming, etc. $6,000,000 10/1/2006 1/31/2006
Lining of Al Kamaliyah canal in Karba IR-014
Kerbala Lining of Al Kamaliyah canal in Karba with .1 m thick concrete including earth works to complete the required canal sections such as excavation, backfilling, trimming, etc. $300,000 10/1/2006 1/31/2006
Makhmoor Project IR-021
Arbil Irrigation by pumping from Tigris. Project located on left side of Tigris River in Makhmoor areas. Total area = 55000 hac. To increase the agricultural land. This project will change rain feel area to irrigated area in five places: 1. Makhmoor Project 2. Zab river plains 3. Tigris river plain by mean of feeder canal off taking from u/s of ifraz weir the canal length 84km the other places 4. Tigris river plain in Abasian 5. Tigris river plain near Zab Areas are irrigated by direct pumping. The project located S.E. of Mosul on left bank of Tigris, Greater Zab in north and Tigris River in East and Lower Zab in the South and in the east Karajook. $15,000,000 8/1/2006 1/31/2007
Provide pumps for Hafria Drainage Pumping Station PS-033 W-R-WR-PS and G-271 Wassit Provide pump capacity to remove and convey drainage water. Provide vertical pumps with unit capacity of 1.5 CMS. Projected head equals 8.0 meters. Includes the following: pumps and motors complete, electrical installation, cables, and complete sets of accessories. Pumps to be installed within new pump house. $3,198,000 8/1/2006 8/1/2007
Provide pumps for Hafria Drainage Pumping Station PS-027 W-R-WR-PS and G-244 Wassit Provide pump capacity to remove and convey drainage water. Provide vertical pumps with unit capacity of 1.6 CMS. Projected head equals 8.0 meters. Includes the following: pumps and motors complete, electrical installation, cables, and complete sets of accessories. Pumps to be installed within new pump house. $3,198,000 6/1/2006 6/1/2007
Provide pumps for Hilla Irrigation Project (North Hussinia Drainage Pumping Station) PS-032 W-R-WR-PS and G-150 Babylon Provide pump capacity to convey drainage water. Provide vertical pumps with unit capacity of 1.75 CMS total station capacity. Projected head equals 10.0 meters. Includes the following: pumps and motors complete, electrical installation, cables, and complete sets of accessories. $1,794,000 8/1/2006 8/1/2007
Provide pumps for Hussina Beni Hassan Irrigation Project (North Pump Station) PS-031 W-R-WR-PS and G-152 Kerbala Provide pump capacity to remove and convey drainage water. Provide vertical pumps with unit capacity of 1.75 CMS total station capacity. Projected head equals 10.0 meters. Includes the following: pumps and motors complete, electrical installation, cables, and complete sets of accessories. Pumps to be installed within existing pump house. $959,000 8/1/2006 8/1/2007
Provide pumps for Hussinia Beni Hassan Irrigation Project (Sigilla Drainage Pump Station) PS-038 W-R-WR-PS and G-151 Kerbala Provide pump capacity to remove and convey drainage water. Provide vertical pumps with unit capacity of 1.125 CMS. Projected head equals 17.0 meters. Includes the following: pumps and motors complete, electrical installation, cables, and complete sets of accessories. $497,000 10/1/2006 10/1/2007
Provide pumps for Kesaba Drainage Pumping Station PS-030 W-R-WR-PS and G-245 Wassit Provide pump capacity to remove and convey drainage water. Provide vertical pumps with unit capacity of 0.93 CMS. Projected head equals 4.6 meters. Includes the following: pumps and motors complete, electrical installation, cables, and complete sets of accessories. Pumps to be installed within existing pump house. $1,723,000 8/1/2006 8/1/2007
Provide pumps for Khalis Irrigation and Drainage Project, Lower Khalis Irrigation P.S. PS-040 W-R-WR-PS and G-163 Diyala Provide pump capacity for local irrigation to increase the agricultural lands. Provide vertical pumps with unit capacity of 5.0 CMS. Projected head equals 21.0 meters. Detailed design required. Includes the following: pumps and motors complete, electrical installation, cables, complete sets of accessories, and new civil works. $23,982,000 10/1/2006 10/1/2007
Provide pumps for Samawa Irrigation Project (Swair Irrigation Pumping Station) PS-037 W-R-WR-PS and G-148 Muthanna Provide pump capacity for local irrigation. Provide horizontal pumps with unit capacity of 2.0 CMS. Projected head equals 10.0 meters. Includes the following: pumps and motors complete, electrical installation, cables, and complete sets of accessories. This will replace the existing pumping station. $6,662,000 10/1/2006 10/1/2007
Provide pumps for Shehamia Drainage Pumping Station PS-029 W-R-WR-PS and G-242 Wassit Provide pump capacity to remove and convey drainage water. Provide vertical pumps with unit capacity of 1.6 CMS. Projected head equals 4.45 meters. Includes the following: pumps and motors complete, electrical installation, cables, and complete sets of accessories. Pumps to be installed within new pump house. $1,723,000 8/1/2006 8/1/2007
Provide pumps for Sheikh Lengar Reclamation Project Major-040 W-R-WR-Major-220 Diyala To reclaim agricultural land and reduce losses from the canal network. Improve channel lining for irrigation project serving 3,350 Ha. Construct concrete lined channels and related structures. $142,824,000 8/1/2006 1/31/2007
Provide pumps for Tarmiya Drainage Pumping Station PS-028 W-R-WR-PS and G-166 Salah al-Din Provide pump capacity for local drainage pumps to protect adjacent lands from inundation. Provide vertical pumps with unit capacity of 2.25 CMS. Projected head equals 7.75 meters. $2,842,000 8/1/2006 8/1/2007
Ramadi Irrigation Pumping Station No. 01 Rehabilitation PS-036 W-R-WR-PS and G-145 Anbar Provide pump capacity for local irrigation. Rehabilitate the Ramadi drainage pumping station Number 01. Provide three (3) vertical pumps with unit capacity of 0.75 CMS. Projected head equals 13.0 meters. Includes the following: pumps and motors complete, electrical installation, cables, and complete sets of accessories. $471,000 3/15/2006 9/30/2007
Ramadi Reclamation Project (No. 2) Major-024
Anbar Construction including lining, land leveling and addition of structures to increase and improve the agricultural lands. $15,000,000 6/1/2006 11/30/2006
Rehabilitation of Dijella Projects (9,10,11) - Various Projects Major-030
Wassit Project is for irrigation and drainage lands in Southern Iraq. Includes lining of concrete canals, also fill drains, main drains, precision land leveling. Reclamation of 10000 hac. `It has been estimated based on historical reclamation projects that the cost generally averages 1500 per hectare. This price includes all lining. $10,000,000 1/1/2006 6/30/2007
Rehabilitation of Musaib Project - Lining and field drains. Major-037
Babylon Lining and field drains; to improve and increase the agricultural land. Total project area = 84250 ha. $10,000,000 8/1/2006 1/31/2008
Rhauda Dam Construction Dam-021 W-R-WR-Dam Rural-185 Anbar Construction of earth fill dam on Wadi Al Ghadaf in the western desert. Dam would be 1,245 meters in length, 11.5 meters in height, and would provide 6.9 Million CM of storage with an ungated concrete spillway and bottom outlet. $4,032,000 1/1/2006 8/31/2007
Rutba Dam Maintenance Dam-022
Anbar Maintenance for Rutba Dam and construction of an office for the resident engineer in Rutba. $70,000 5/1/2006 9/1/2007
Saragawa Project IR-023
Suliamaniyah To improve and increase the agricultural lands $10,000,000 6/1/2006 11/30/2006
Selevanee Plane and Small Projects IR-022
Duhuk To improve and increase the agricultural lands $2,000,000 6/1/2006 11/30/2006
Shamamouk Irrigation Project IR-018
Arbil To increase the agricultural land. $4,000,000 1/1/2006 6/30/2007
Tak Tak Dam Construction Dam-018
Arbil Construction of reregulating earth dam downstream from Dokan dam. Purpose of dam is for storage of water, agriculture, power generation, and flood control. Dam to be located 6km upstream of Arbil government. Upper level = 423m, storage level =415m, total height = 100m. $1,000,000,000 6/1/2006 11/30/2007
Vehicles Equip-011
Nationwide The Ministry will need several different types of equipment to perform this function such as: 50 FPS vehicles (landcruiser or double cab trucks) 100 Station landcruisers 500 dual cab hi-lo type trucks $12,150,000 3/1/2006 3/1/2006
Wadi Al Nafat Dam Construction Dam-012 W-R-WR-Dam Rural-189 Diyala The Wadi Al Nafat Dam is used for irrigation and water storage for drinking water. This will provide water to the Bedwin people and their sheep. Construction of earth fill dam on Wadi Al Nafat in the eastern region. $8,882,000 6/6/2006 11/30/2006
Zakho Project IR-019
Duhuk To improve and increase the agricultural lands. Total project area = 13400 hac. Irrigated by pumping and gravity from Khabour River the farm irrigation (gravity, sprinklies, drip) Cropping intensity = 128% $7,500,000 6/1/2006 11/30/2007